Treswell, Nr Retford - September 2021

This site is now weathertight and secure with the 1st fixtrades well underway and plasterers due to start.

This site is now weathertight and secure with the 1st fixtrades well underway and plasterers due to start.

Foundations, Framework and Construction Start

March 2021

Construction Completion

July 2021

Watertight & Security

July 2021

2nd fix internal and external works

August / September

Completed new build

April / May 2022